Polycom RealPresence Collaboration Server (RMX) 1500/2000/4000 Administrator’s Guide
21-16 Polycom, Inc.
2 In the MCMS_PARAMETERS tab, double-click or select the flag
FORCE_CIF_PORT_ALLOCATION and click the Edit Flag button.
3 In the New Value field, clear the value entries.
4 Click OK.
Reset the MCU for changes to take effect. For more details, see the RealPresence Collaboration
Server (RMX) 1500/2000/4000 Administrator’s Guide, "Resetting the RMX” on page 21-69
Resource Report
The Resource Report displays the real time resource usage according to the selected Resource
Capacity Mode:
Flexible Resource Capacity Mode available in MPM, MPM+ and MPMx Modes.
Fixed Resource Capacity Mode available only in MPM+ and MPMx Modes
The Resource Report also includes a graphic representation of the resource usage. One
resource report is available for all resource usage including SVC-based endpoints.
When the MCU is working in MPM+ or MPMx Mode with Fixed Resource Capacity Mode™
selected, additional system resources information is displayed.
Displaying the Resource Report
1 In the main toolbar, click Administration > Resource Report.
The Resource Report dialog box is displayed, showing the resource usage according to
the Resource Capacity Mode. For each resource type, the Resource Report includes the
following columns:
On the RMX1500 MPMx-Q assembly, the use of HD with Continuous Presence requires an
additional license. In the Resource Report and Resolution Configuration panes, HD settings are
displayed but are not enabled and if HD is selected the system will enable SD by default.
Table 21-6 Resource Report Fields Parameters
Column Description
Type The type of audio/video resources available. This applies to both
AVC and SVC-based endpoints (and resources).
Total The Total column displays the total number of resources of that type
as configured in the system (Occupied and Free). This number
reflects the current audio/video port configuration (for AVC and SVC-
based conferencing). Any changes to the resource allocation will
affect the resource usage displayed in the Resource Report.