![](https://pdfstore-manualsonline.prod.a.ki/pdfasset/2/07/207ea955-b0a5-4690-afdf-8b9461a5122e/207ea955-b0a5-4690-afdf-8b9461a5122e-bg257.png)
DEFINITY Enterprise Communications Server Release 7
Maintenance for R7r
555-230-126
Issue 4
June 1999
Maintenance Commands
8-288status pgate-port
8
Output
The following display shows a typical result when
status periodic-scheduled
is
entered.
status pgate-port
status pgate UUCSSpp [print]
Percentage
Complete
The ratio of the number of maintenance objects tested to the total
number of maintenance objects tested during a cycle. For periodic
tests, the ratio is for the current cycle, if active; or for the last
completed cycle if not. For scheduled tests, the ratio is for the last
completed cycle.
System
Critical
System critical resources are those whose health affects the entire
system such as the processor. These are always tested first.
Shared
Resource
Shared resources are those that are used by many users, such as
trunks. These are tested after system critical resources.
Single User
Single User resources are those whose health affects only one
user, such as voice stations.
Pre- SCHEDULED
MAINTENANCE
The system can be administered to perform interchanges of
duplicated components and backup of data to disk before daily
scheduled maintenance begins. This is pre-scheduled
maintenance and is administered on the
change
system-parameters maintenance
form.
status periodic-scheduled
MO Current Current Previous Cycle Rate of
Type Cycle % Cycle Duration Completed
Complete Active? (hr:min:sec Cycles
PERIODIC System Critical 80% y 00:00:48 1.0/hr
MAINTENANCE Shared Resource 100% n 00:00:43 1.0/hr
Single User 100% n 00:00:48 1.0/hr
Total 00:01:57
Start Time of Current or Previous Cycle: 11/19/13:34:36
Pre-SCHEDULED MAINTENANCE n 00:08:15
SCHEDULED System Critical 100% n 00:02:15 1.0/day
MAINTENANCE Shared Resource 100% n 00:03:16 1.0/day
Single User 100% n 00:20:05 1.0/day
Total 00:25:36
Start Time of Current or Previous Cycle: 11/18/22:00