Emerson Process Management 2400S Satellite Radio User Manual


 
92 Micro Motion
®
Model 2400S Transmitters for DeviceNet
Measurement Performance
During meter verification, you can choose between setting digital communications process variable
values to the configured fault indicator or the last measured value. The values will remain fixed for
the duration of the test (approximately four minutes). Disable all control loops for the duration of the
procedure, and ensure that any data reported during this period is handled appropriately.
To perform meter verification:
Using ProLink II, follow the procedure illustrated in Figure 10-1.
Using the display menu, follow the procedure illustrated in Figure 10-2. For a complete
illustration of the meter verification display menu, see Figure B-8.
Using a DeviceNet tool, follow the procedure illustrated in Figure 10-3.
For a discussion of meter verification results, see Section 10.3.1.
Figure 10-1 Meter verification procedure – ProLink II
Verify configuration
parameters
Tools >
Meter Verification >
Structural Integrity Method
View previous test data
Next
Enter optional test data
Initialize and start meter
verification
Next
Abort
Next
Fault
configuration
Hold last
value
Progress bar shows
test in progress
Next
Finish
(2)
Graph of results
Rerun
test?
Yes
PassFail
No
Start
Back
(1)
View report (option to print
or save)
Back
Abort
(1) If the graph was viewed at the beginning of the procedure,
clicking Back here will return to the beginning of the procedure
(along the dotted line).
(2) The results of the meter verification test are not saved until
Finish is clicked.