131
Figure 27. Fibre Channel Switch Module Locations
4. If the blade server is operating, press the power-control button (behind the blade server control panel
door) to shut down the operating system and turn off the blade server. For the location of the control panel
door, see the illustration on page 132 Wait at least 30 seconds, until the drives stop spinning, before
proceeding to the next step.
5. Open the two release levers. The blade server moves out of the bay approximately 0.6 cm (0.25 inch).
6. Pull the blade server out of the blade bay. Spring-loaded doors further back in the bay move into place to
cover the bay temporarily.
7. Place either a filler blade or another blade server in the bay within 1 minute. The recessed spring-loaded
doors will move out of the way as you insert the blade or filler blade.
✏ NOTE
The installation procedure in this manual is applicable to the Intel
®
Server Compute Blade SBXL52
and should be used as a reference. When installing the FC Expansion Card in other Intel
®
Server
Compute Blades, refer to the Installation and User’s Guide for that product.
8. Lay the blade server down on a flat, nonconductive surface, with the cover side up.
9. Press the blade-cover release on each side of the blade server. Open the cover and lay it flat, or
lift it from the blade server.
Hazardous energy is present when the blade is connected to the power source. Always replace the
blade cover before installing the blade.