APC 480 Stereo System User Manual


 
InfraStruXure System - Installation and Start-Up 5
Site Planning
Space Considerations
Use the figure below to determine the space requirements for installing the InfraStruXure PDU,
Symmetra PX UPS, and XR Battery Enclosure. Consult local codes and the NEC for additional
requirements.
Minimum Front Clearance
208 V 914 mm/36 in
480 V:1067 mm/42 in
Minimum Rear Clearance
208 V:914 mm/36 in
480 V:1067 mm/42 in
Ceiling Clearance
>304 mm/12 in