Start-Up Procedure: Apply power to the system
34 InfraStruXure System - Installation and Start-Up
Verify proper voltage and phase rotation at the UPS
1. Close (turn ON) the Q1 circuit breaker on the PDU to apply power to the UPS.
2. Ensure A-B-C clockwise rotation at the UPS input terminal block, using a phase rotation meter.
3. Verify proper voltage is present at the UPS input terminal block (208V, metered phase-to-phase),
using a true RMS voltmeter.
Start the UPS
1. Set the UPS DC Disconnect circuit breaker to ON, and then set the
UPS System Enable switch to ON.
2. If applicable, set the XR Battery Enclosure DC Disconnect
circuit breaker to ON.
When the System Enable switch is in the ON position, the
Startup screen appears on the display interface of the Symmetra
PX UPS.
Then, the top-level status screen appears on the display interface.
This may take up to 40 seconds.
px0013a
PowerView RM
Rev: 000 English
Please wait...
Fuel %
Load %
Runtime:
||||||||||||
|||
1hr 2m
In 208V out000V 60Hz