Start-Up Procedure: Apply power to the system
32 InfraStruXure System - Installation and Start-Up
Verify UPS battery operation
1. Read the messages displayed on the
Symmetra PX UPS display interface. Note
any alarms and verify that they are
appropriate for start-up conditions.
Top-Level Status Screen
2. Command the UPS to apply power to the
load:
a. Press the
ESC key to open the top-level
menu.
b. Select Control, and press the
ENTER key.
Top-Level Menu
c. Select Turn Load On from the Control
menu, and press the
ENTER key.
Control Menu
d. On the next screen: select Yes, UPS Load
ON, and press the
ENTER key.
Confirmation Screen
The interface will display the following
screen:
The interface will display the following fault
message:
e. Select Start Now, and press the
ENTER key.
The interface will display the following
screen:
The LOAD ON LED illuminates and the
interface displays the following screen:
After you have verified that the UPS operates correctly in battery operation, shut down the UPS:
Fuel %
Load %
Runtime:
||||||||||||
|||
1hr 2m
In 208V out000V 60Hz
Control
Status
Setup
Accessories
Logging
Display
Diags
Help
UPS Into Bypass
Do Self Test
Simulate Power Fail
Graceful Reboot
Graceful Turn Off
Start Runtime Cal
Turn Load On
Confirm
Yes, UPS Load ON
No, Abort
UPS has been
commanded to turn
load power on...
Low/No AC input
Start up on Batt?
Start Now
Abort Start-up
UPS has been
commanded to turn
load power on...
UPS load is on
Press any key...