• 18 releasable cable ties shown in Figure 1-2.
Figure 1-2 Releasable Cable Tie
• The fasteners specified in Table 1-1.
Table 1-1 Fasteners
DescriptionTorqueFormatSizeQuantity
Cage nut for M6 screw.N/ASquare nutM6 cage nuts2
Machine screw. For use with M6 cage nut.25-30 in/lbPosidriveM6 x 16 mm
pan head screws
2
To prevent screws from becoming loose because of vibration, HP recommends that you use
an adjustable torque drive, set to the torque specifications given in Table 1-1. Contact your
HP sales representative if any parts are missing.
1.5 Required Resources
To install the HP cable management kit, you require the following resources:
• Tools:
— Screwdriver, #2 (medium) Phillips
— Cage-nut insertion tool (shipped with the rack) or a flat-headed screwdriver
— Marker pen or masking tape
— Diagonal cutting pliers
• Resources: Cables of the type used by the InfiniBand switch.
1.6 Prerequisites
Before you begin to mount the bracket:
• Follow the cable-handling precautions for InfiniBand cables. For more information, see the
HP Cluster Platform InfiniBand Interconnect Installation and User's Guide at:
http://www.docs.hp.com/en/highperfcomp.html
• Obtain the set of cabling tables required for your solution (if applicable).
• Read the hardware installation guide for the InfiniBand switch you are installing.
6 Preparing for Installation