IBM SG24-7645-00 Speaker System User Manual


 
7645ProjPlan.fm Draft Document for Review May 23, 2008 10:14 am
24 Maximo Essentials V7.1 - Implementer’s Guide
Creation of users, roles and security groups
Configure role based start centers
Creation of Job plans, work orders
Configuration of the tool to map to business processes which includes, but
is not limited to:
Addition or deletion (as the case may be) of fields on screen and
database
Create communication templates
Create escalation points and define SLAs in the system
Create and test data migration scripts
Migrate data from its existing source to Maximo
Build integration interfaces - either using custom code or MEA (as the
case may be)
Creation and deployment of reports
Phase 4: Testing and Go-Live
Role Involved: Project Manager, Solution Architect, Testers, Maximo Developers
Optional Roles: DBA, Application Server Specialist
Key Activities:
Tes ting
The first key task is migration from development environment to test
environment. Depending on the customer’s environment and the complexity of
implementation, customer may decide to use automated tools for testing or a
manual approach, nevertheless all or some of the following types of testing
needs to be carried out:
Functional Testing
Test validations in new fields
Test emails being sent on escalations
Test accuracy of data flowing between modules in the system
Test data accuracy in reports
System Integration Testing
Test accuracy of data coming from external systems
Test accuracy of data going into external systems
Scenario testing to ensure there is nothing that affects availability of
any system
Performance Testing
Page Load time
Peak load